Fresh Water Pipe Lines

Value of Contract  95,000,000.000 K.D

Date of Enterprise 18/10/2012

Date of Handing over  17/06/2015

Scope of Work

 

This Contract comprises of Supply , Construction And Maintenance Of 4 X 1600 mm Dia. Fresh Water Pipe Lines From Azzour WDC II  To Mina Abdullah WDC II

including all required connections to the existing pipe lines.

The works shall include but not limited to the following:

  1. Supply and Lay of 140 KM D.I Pipes 1600 mm Dia. and annexed fitting.
  2. Excavation and Cast in site of 144 No. Reinforced concrete valve chambers.
  3. Excavation and Cast in site of 17 No. Reinforced concrete Thrust Blocks.
  4. Supply and Lay of 600 KM fiber optical cables .
  5. Pipe Jacking for road crossing.
  6. Carryout, and commissioning of the cathodic protection system for the pipes.
  7. Protective the pipes with tape wrapping coated.