Fresh Water Pipeline From Wafra Reservoir

Value of Contract  4,966,000.000 K.D

Date of Enterprise  21/04/2014

Date of Handing over  20/10/2015

Scope of Work

 

This Contract comprises of the Construction and Maintenance of  1200 mm dia Fresh Water Pipeline From Wafra Reservoir To Subah Al Ahmed City.

The works shall include but not limited to the following:

1).Take delivery of materials from MEW stores ,Installation, Construction, Completion and Maintenance of 1200 dia ductile iron pipe line (approx.19km) within the MEW reservation area from Wafra reservoir to the tie in points of subah al ahmed water towers for supplying water from wafra reservoir to subah al ahmed water towers

2). Take delivery of materials from MEW stores, Installation, Construction, Completion and Maintenance of 800 dia ductile iron pipe line(approx.9km) within the MEW reservation area from Wafra reservoir to the tie in points of Wafra Residential Area for supplying water from the wafra reservoir to the Wafra residential area.