Jaber Al Ahmad Al Jaber Al Sabah Hospital

Value of Contract   303,998,000.000 K.D

Date of Enterprise  15/12/2009

Date of Handing over  14/12/2013

Scope of Work

 

This Contract comprises of the Construction, Completion, Commissioning, Handover and Maintenance of All the Buildings and External Works.

The scope also includes All Fixed and Moveable Furniture, All Furnishing and All Equipment but not the Medical Equipment.  However, the bed head units are included in Package 2 Scope of Work.

The works comprise of complete Civil, Structural, Architectural, MEP and External Works as well as all temporary works.

The following buildings are a part of this Contract :

1.Hospital Building

2.Parking Building

3.Central Plant

4.Dental Building with Shelter

5.Residential Building

The External Works shall include all works such as Hard and Soft Landscaping, all Utilities, All Tanks, All Enclosures etc , all External Electrical and Mechanical Works and all Boundary walls including Gates.

The works shall include but not limited to the following:

The Hospital Building (1200 Beds)

The Building area is 47000 m2 and consists of:2 basement levels ,Ground Floor,12 floors

The Total Built-up area: 475000 m2

 The Dental Building:

The building area is 5000 m2 and consists of: Basement Level & Ground Floor

The Total Built-up area : 13000 m2

 The Residential Building:

The building area is 2000 m2 and consists of: Ground Floor&3 Floors

The Utility Building (Electro-Mechanical Services) : 20000 m2

The Laundry: 2500 m2

The Medical Gas System Building: 750 m2

Under-ground Water Tank: 5700 m2

The Parking Building Total area 212000 m2  , 3 -underground levels -Total capacity: 7000 cars

Total Project Land Area: 225000 m2 – Total Built-up Area 660000 m2

Raft Foundation Volume: 370000 m3

Excavation Volume: 900000 m3 – Plain Concrete Volume: 50000 m3

Reinforced concrete Volume: 600000 m3 -Reinforced Carpentry Total Area: 1500000m2

Concrete Pouring Rate: 1000 m3/day -Reinforced Carpentry Rate: 2000 m2/day

Reinforcement Rate: 120 Ton/day

Back